South Dakota post-storm inspection checklist
Follow-up after a storm that causes runoff, or the storm size the permit names, focused on where water went and what controls failed.
Based on: South Dakota DANR General Permit SDR100000: inspection and corrective action requirements
When you print this page, you get a clean blank form for the field without the rest of the website around it.
Storm
| Item | Pass | Fail | N/A |
|---|---|---|---|
| Rainfall amount and date recorded (site rain gauge or the weather station named in the SWPPP) | |||
| Inspection made within the time the permit allows after the storm, or the reason it wasn't |
Discharges
| Item | Pass | Fail | N/A |
|---|---|---|---|
| Each discharge point observed; any sediment, turbidity or sheen described Photo | |||
| Receiving water or storm drain downstream checked for sediment deposits |
Controls
| Item | Pass | Fail | N/A |
|---|---|---|---|
| Perimeter controls intact after the storm: no breaches, undercutting or overtopping Photo | |||
| Inlet protection intact and not clogged; sediment removed Photo | |||
| Sediment basins and traps have capacity for the next storm | |||
| Track-out cleaned from streets after the storm | |||
| Slopes and stabilized areas free of new rills and gullies | |||
| Washouts and stockpiles not washed out or overflowing |
Follow-up
| Item | Pass | Fail | N/A |
|---|---|---|---|
| Every failure found entered as a corrective action with a fix date |
Photo A photo is expected with this item.
Skip the clipboard next time. Scan to try this inspection on your phone in the inspectorjay demo: geotagged photos, dictated notes, a pass or fail on every item, and the report emailed to the contractor before you leave the site.
demo.inspectorjay.com/app · inspectorjay.com
This checklist is a starting point. Check each item against your current permit and your agency's standards before relying on it. Based on the South Dakota DANR General Permit for Storm Water Discharges Associated with Construction Activities (SDR100000). Check each template against the current permit and your local requirements before relying on it.
Know when these checklists change
Permits and standards are reissued every few years, and the inspection requirements change along with them. Leave your email and we'll let you know when we update the South Dakota checklists or add new ones, which is a few emails a year at most.
You're on the list. We'll email you when the South Dakota checklists change.
That didn't go through. Check your email address and try again, or write to hello@inspectorjay.com.
Fill it in on your phone instead
In inspectorjay, each item gets a pass or fail, a dictated note, and geotagged photos, and the finished report goes to the contractor before you leave the site instead of waiting for the clipboard to make it back to the office.